|
Complex 3D design and contamination overcome for Canada Life in
central Leeds
-
Structural Consultancy Services
The steel frame has recently been completed for an eye-catching
glass clad £10 million building on a former gas works site
in central Leeds, which is being re-developed by Canada Life. Significant
ground and structural design challenges were overcome by structural
engineers Bettridge Turner and Partners (formerly GBP) to deliver
the design provided by architects Watkins Gray International.
According to Chris Jarvis of Watkins Gray International, “BT&P
had no difficulty interpreting our design requirements and quickly
rose to the challenges presented during the project. They were very
pro-active in developing innovative solutions to the structural
design and contamination issues”.
To maximise the passage of light through the glass clad structure,
it includes an open lift shaft with a glazed lift car and a moment
connection steel frame with composite concrete floors. Without the
benefit of cross bracing, the steel frame posed a complex three-dimensional
design challenge for Bettridge Turner and Partners. The overall
floor depth was kept to a minimum using composite action between
the steel beams and the concrete floors.
The main entrance opens up into a top lit glass atrium, while the
other three elevations feature striking white concrete staircases.
According to Philip Chan, Structural Engineering Director, Bettridge
Turner and Partners, “The thinner walls provided by the absence
of cross bracing gave the architect more freedom to exploit the
benefits of a fully glazed aluminium cladding system”.
The building sits on driven pre-cast concrete piles, pile caps
and ground beams, with an in situ ground bearing concrete slab.
The material excavated to accommodate the foundations and to adjust
ground levels was treated with cement and reused on site, following
changes in regulations regarding the disposal of contaminated soil.
more projects
|